Home/Q&A/Lead time and MOQ

What is the lead time and minimum order?

Five working days from deposit on regular sizes, and one 20 ft container — roughly 25 t — as the normal minimum.

Lead time

The clock starts when the deposit reaches the mill, not when the enquiry arrives. For regular sizes (12.7 / 15.2 / 15.7 mm, 1860 MPa, GB/T 5224) the strand is already wound and packed, so the five days cover final inspection, marking, documentation and loading.

Anything outside the standard run changes the picture: a different standard, a galvanised or unbonded construction, a special coil weight, or cut-to-length tendons. Those are scheduled into the mill's production plan, and we give you a firm date before you place the order rather than a hopeful one after.

Minimum order

One 20 ft container. At 3.0–3.5 t per coil that is about seven or eight coils, roughly 25 t. Below a container load the sea freight and the fixed costs per tonne climb quickly, which is why we do not pretend small lots are cheap.

If you are testing a supplier, a single container is a reasonable trial order: it is enough to run a real project, and small enough not to lock up much capital.

Mixing sizes

Two or three diameters in one container is routine — 15.2 mm for the main tendons and 12.7 mm for the smaller elements, for example. We confirm the weight and the coil layout before booking, because a 20 ft box has a hard limit and strand is dense.

Customs and border clearance time is separate from production time. Ask for the transit estimate for your route when you request the quote — see delivery into Pakistan.